the five stages of general contracting — from briefing to handover
2026. március 26. · 9 min
next article
construction · 8 min
knowledge
A curated monthly mix on SIP technology, energy efficiency, regulatory changes, and construction pitfalls. Ad-free — unsubscribe in a click.
Want to narrow the topics? advanced options →
process
2026. március 26. · 9 min
next article
construction · 8 min
For the client, general contracting runs as a single contract and a single point of contact. Behind the scenes, a five-stage process generates different decisions and different documents at each stage. This article walks through what the process means for the client — in time, in cost, and in responsibility.
The process opens with one or two deeper conversations. We learn the goal, the budget, the schedule expectation, and the client's life. A site walk, plot and orientation analysis. We pull the local building authority's regulations and check utility-connection options with the council and providers.
briefing — output
Two or three parallel concepts at sketch level — plan, mass model, openness and orientation. The client doesn't pick a variant; they find their direction through a conversation. The structural choice (SIP or traditional), the rough material palette, and the primary building-services system are decided here.
From the chosen concept we develop the permit and construction document set. It includes the structural calculation, the building-services design, the energy certificate, the fire-protection plan, and the utility-connection documentation. The agency coordination (council, building authority, utilities) we lead — the client doesn't sit across from a clerk.
The "6–16 weeks" range depends on region and authority load. In the Pest county green belt, typically 8–10 weeks; in tougher cases (landscape protection, water authorities, heritage) 12–16 weeks.
Construction begins after the building permit is final. The slab takes 2–4 weeks, the SIP shell 8–12 weeks, building services and interior finish 3–5 months. A single-storey 140 m² SIP home runs 8–9 months end-to-end; a two-storey 240 m² home, 11–13 months; a 600 m² bespoke design, 18–24 months.
During construction the client receives a weekly written progress report — photos, milestones, material-sample approval requests, budget status. There is also a weekly site walk with the client.
Every week the client should feel they can see into the process. If they don't, that's a communication failure — not a technical one.
Technical handover is a two-week process: the client (or their appointed expert) compiles a snag list, we resolve it, second walkthrough. After handover, we administer the occupancy certificate. The mandatory year-end technical walkthrough lets us review together: what survived a season, what wants tuning.
handover — documents
| stage | duration | cumulative | |---|---|---| | briefing | 3 weeks | end of week 3 | | concept | 6 weeks | end of week 9 | | permitting | 9 weeks | end of week 18 (~4.5 months) | | construction | 7 months | ~11.5 months | | handover | 2 weeks | ~12 months |
The 12 months is an average; the specific plot and program shift the numbers. At quote we give a project-specific schedule with both ends of the range.
The process runs through five stages because each stage demands a different type of decision from the client and yields a different type of document. One contract and one point of contact does not mean the client doesn't decide — it means a single team of specialists guides those decisions, in coordinated form, end to end.